Clocaenog Forest Wind Farm

    Innogy Renewables UK Limited
    Current strike price
    92.80£/MWh
    Initial Strike Price
    82.50£/MWh
    Change to Strike Price (where applicable)
    10.30£/MWh
    Company Registered Address

    Windmill Hill Business Park
    Whitehall Way
    Swindon
    Wiltshire
    SN5 6PB
    United Kingdom

    Date CFD Register Entry was Last Updated
    Allocation round
    Allocation Round 1
    Unique Identifier
    AAA-CLO-186
    Technology type
    Onshore Wind
    CFD Unit with Combined Heat and Power ("CHP") (yes/no)
    No
    Dual Scheme Plant
    No
    Initial Installed Capacity Estimate for CFD Unit
    96.00MW
    Target Commissioning Date
    Target Commissioning Window Start Date
    Generator’s Expected Start Date
    Any Reduction to the Capacity of a CFD Unit
    0.00MW
    Company Registration No
    2550622
    Unique Geographical Coordinates
    N: 53.113, -3.479; E: 53.057, -3.453; S: 53.043, -3.475; W: 53.098, -3.494
    CFD Agreement Type (Bespoke, Investment, Generic, Private Network, Phased (Single Metering) or Phased (Apportioned)
    Generic
    Version Name and Number of Standard Terms
    Version 1, 29 August 2014
    Reference Number for Modification Agreement
    N/A
    Type of Connection (Partial, Direct or Islanded)
    Direct
    Transmission or Distribution connection
    Distribution
    "Licence Exempt Embedded" or "Licence Connected" (applies to distribution connected only)
    Licence Exempt Embedded