Dogger Bank C P2

Doggerbank Offshore Wind Farm Project 3 Projco Limited

Relevant Dates

Date CFD Register Entry was Last Updated
Target Commissioning Date
Target Commissioning Window Start Date
Generator’s Expected Start Date

Strike price

Initial Strike Price
41.61£/MWh
Change to Strike Price (where applicable)
6.48£/MWh
Current strike price
48.09£/MWh

Project Information

Allocation round
Allocation Round 3
Technology type
Offshore Wind
CFD Unit with Combined Heat and Power ("CHP") (yes/no)
No
Dual Scheme Plant
No
Initial Installed Capacity Estimate for CFD Unit
441.00MW
Unique Geographical Coordinates
N: 55.119, 3.099; E: 55.119, 3.099; S: 54.955, 3.032; W: 55.020, 2.806
CFD Agreement Type (Bespoke, Investment, Generic, Private Network, Phased (Single Metering) or Phased (Apportioned)
Phased (Single Metering)
Version Name and Number of Standard Terms
Version 3, 1 May 2019
Reference Number for Modification Agreement
N/A
Type of Connection (Partial, Direct or Islanded)
Direct
Transmission or Distribution connection
Transmission
Single Metering or Apportioned Metering (applies to phased offshore wind only)
Metered
Offshore Leasing Round 2 or 3/Scottish Territorial Waters (applies to Offshore Wind only)
Round 3
General comments
Following the conclusion of the Judicial Review that was impacting all AR3 contracts, this contract was afforded a 6 month extension to the CFD milestones of Milestone Delivery Date, end of Target Commissioning Window and Longstop Date.