Dorenell Limited
Current strike price
91.94 £/MWh
Initial Strike Price: 82.50 £/MWh
Change to Strike Price (where applicable): 9.44 £/MWh
Company Registered Address
16 West Borough
Wimborne
BH21 1NG
United Kingdom Date CFD Register Entry was Last Updated 25/01/2019 Allocation round Allocation Round 1
Unique Identifier AAA-DOR-182 Technology type Onshore Wind CFD Unit with Combined Heat and Power ("CHP") (yes/no) No Dual Scheme Plant
No
Initial Installed Capacity Estimate for CFD Unit 177.00MW
Target Commissioning Date 30/04/2018 Target Commissioning Window Start Date 15/04/2018
Any Reduction to the Capacity of a CFD Unit 0.00MW
Start Date
20/12/2018
Company Registration No 5628395 Unique Geographical Coordinates N: 57.379, -3.097; E: 57.377, -3.096; S: 57.317, -3.138; W: 57.324, -3.170 CFD Agreement Type (Bespoke, Investment, Generic, Private Network, Phased (Single Metering) or Phased (Apportioned) Generic
Version Name and Number of Standard Terms Version 1, 29 August 2014 Reference Number for Modification Agreement N/A
LCCC's Reasons for Accepting an Application to Modify the Standard Terms N/A Type of Connection (Partial, Direct or Islanded) Direct Transmission or Distribution connection Transmission