Dudgeon Phase 2

Dudgeon Offshore Wind Limited

    Relevant Dates

    Date CFD Register Entry was Last Updated
    Target Commissioning Date
    Target Commissioning Window Start Date
    Start Date

    Strike price

    Initial Strike Price
    150.00£/MWh
    Change to Strike Price (where applicable)
    20.03£/MWh
    Current strike price
    170.03£/MWh

    Project Information

    Allocation round
    Investment Contract
    Technology type
    Offshore Wind
    CFD Unit with Combined Heat and Power ("CHP") (yes/no)
    No
    Dual Scheme Plant
    No
    Initial Installed Capacity Estimate for CFD Unit
    210.00MW
    Any Reduction to the Capacity of a CFD Unit
    0.00MW
    Unique Geographical Coordinates
    N: 53.315, 1.343; E: 53.268, 1.447; S: 53.210, 1.429; W: 53.301, 1.321
    CFD Agreement Type (Bespoke, Investment, Generic, Private Network, Phased (Single Metering) or Phased (Apportioned)
    Investment
    Version Name and Number of Standard Terms
    Investment Contract
    Reference Number for Modification Agreement
    N/A
    Type of Connection (Partial, Direct or Islanded)
    Direct
    Transmission or Distribution connection
    Transmission
    Single Metering or Apportioned Metering (applies to phased offshore wind only)
    Metered
    Offshore Leasing Round 2 or 3/Scottish Territorial Waters (applies to Offshore Wind only)
    Round 2