Energy Works (Hull)

Energy Works (Hull) Limited

Relevant Dates

Date CFD Register Entry was Last Updated
Target Commissioning Date
Target Commissioning Window Start Date
Generator’s Expected Start Date
Start Date

Strike price

Initial Strike Price
119.89£/MWh
Change to Strike Price (where applicable)
17.38£/MWh
Current strike price
137.27£/MWh

Project Information

Allocation round
Allocation Round 1
Technology type
Advanced Conversion Technology
CFD Unit with Combined Heat and Power ("CHP") (yes/no)
No
Dual Scheme Plant
No
Initial Installed Capacity Estimate for CFD Unit
25.00MW
Unique Geographical Coordinates
N: 53.756, -0.329; E: 53.755, -0.327; S: 53.754, -0.327; W: 53.755, -0.328
CFD Agreement Type (Bespoke, Investment, Generic, Private Network, Phased (Single Metering) or Phased (Apportioned)
Generic
Version Name and Number of Standard Terms
Version: 1, 29 August 2014
Reference Number for Modification Agreement
N/A
Type of Connection (Partial, Direct or Islanded)
Direct
Transmission or Distribution connection
Distribution
"Licence Exempt Embedded" or "Licence Connected" (applies to distribution connected only)
Licence Exempt Embedded