Hesta Head Wind Farm

Hesta Head Wind Farm Limited

    Relevant Dates

    Date CFD Register Entry was Last Updated
    Target Commissioning Date
    Target Commissioning Window Start Date
    Generator’s Expected Start Date

    Strike price

    Initial Strike Price
    39.65£/MWh

    Project Information

    Allocation round
    Allocation Round 3
    Technology type
    Remote Island Wind
    CFD Unit with Combined Heat and Power ("CHP") (yes/no)
    No
    Dual Scheme Plant
    No
    Initial Installed Capacity Estimate for CFD Unit
    20.40MW
    Unique Geographical Coordinates
    N: 58.783, -2.944; E: 58.777, -2.925; S: 58.772, -2.953; W: 58.772, -2.962
    CFD Agreement Type (Bespoke, Investment, Generic, Private Network, Phased (Single Metering) or Phased (Apportioned)
    Generic
    Version Name and Number of Standard Terms
    Version 3, 1 May 2019
    Reference Number for Modification Agreement
    N/A
    Type of Connection (Partial, Direct or Islanded)
    Direct
    Transmission or Distribution connection
    Transmission