Hesta Head Wind Farm

Hesta Head Wind Farm Limited

Relevant Dates

Date CFD Register Entry was Last Updated
Target Commissioning Date
Target Commissioning Window Start Date
Generator’s Expected Start Date

Strike price

Initial Strike Price
39.65£/MWh
Change to Strike Price (where applicable)
6.18£/MWh
Current strike price
45.83£/MWh

Project Information

Allocation round
Allocation Round 3
Technology type
Remote Island Wind
CFD Unit with Combined Heat and Power ("CHP") (yes/no)
No
Dual Scheme Plant
No
Initial Installed Capacity Estimate for CFD Unit
20.40MW
Unique Geographical Coordinates
N: 58.783, -2.944; E: 58.777, -2.925; S: 58.772, -2.953; W: 58.772, -2.962
CFD Agreement Type (Bespoke, Investment, Generic, Private Network, Phased (Single Metering) or Phased (Apportioned)
Generic
Version Name and Number of Standard Terms
Version 3, 01 May 2019
Reference Number for Modification Agreement
N/A
Type of Connection (Partial, Direct or Islanded)
Direct
Transmission or Distribution connection
Transmission
General comments
Following the conclusion of the Judicial Review that was impacting all AR3 contracts, this contract was afforded a 6 month extension to the CFD milestones of Milestone Delivery Date, end of Target Commissioning Window and Longstop Date.