Hornsea Project 2 Phase 3

Sonningmay Wind Limited

Relevant Dates

Date CFD Register Entry was Last Updated
Target Commissioning Date
Target Commissioning Window Start Date
Generator’s Expected Start Date

Strike price

Initial Strike Price
57.50£/MWh
Change to Strike Price (where applicable)
9.48£/MWh
Current strike price
66.98£/MWh

Project Information

Allocation round
Allocation Round 2
Technology type
Offshore Wind
CFD Unit with Combined Heat and Power ("CHP") (yes/no)
No
Dual Scheme Plant
No
Initial Installed Capacity Estimate for CFD Unit
462.00MW
Unique Geographical Coordinates
N: 53.939, 1.631 E: 53.926, 1.673 S: 53.835, 1.650 W: 53.920, 1.445
CFD Agreement Type (Bespoke, Investment, Generic, Private Network, Phased (Single Metering) or Phased (Apportioned)
Phased (Single Metering)
Version Name and Number of Standard Terms
Version 2, March 2017
Reference Number for Modification Agreement
N/A
Type of Connection (Partial, Direct or Islanded)
Direct
Transmission or Distribution connection
Transmission