Lynemouth Power Station

Lynemouth Power Limited

    Relevant Dates

    Date CFD Register Entry was Last Updated
    Target Commissioning Date
    Target Commissioning Window Start Date
    Start Date

    Strike price

    Initial Strike Price
    105.00£/MWh
    Change to Strike Price (where applicable)
    14.29£/MWh
    Current strike price
    119.29£/MWh

    Project Information

    Allocation round
    Investment Contract
    Technology type
    Biomass Conversion
    CFD Unit with Combined Heat and Power ("CHP") (yes/no)
    No
    Dual Scheme Plant
    No
    Capacity of Whole Station (applicable to Biomass conversions or dual schemes only)
    420.00MW
    Initial Installed Capacity Estimate for CFD Unit
    420.00MW
    Any Reduction to the Capacity of a CFD Unit
    13.21MW
    Unique Geographical Coordinates
    N: 55.209, -1.531; E: 55.205, -1.515; S: 55.202, -1.524; W: 55.204, -1.527
    CFD Agreement Type (Bespoke, Investment, Generic, Private Network, Phased (Single Metering) or Phased (Apportioned)
    Investment
    Reference Number for Modification Agreement
    LP0116A
    Type of Connection (Partial, Direct or Islanded)
    Direct
    Transmission or Distribution connection
    Distribution
    "Licence Exempt Embedded" or "Licence Connected" (applies to distribution connected only)
    Licence Connected