Banks Renewables (Middle Muir Wind Farm) Limited
Current strike price
91.94 £/MWh
Initial Strike Price: 82.50 £/MWh
Change to Strike Price (where applicable): 9.44 £/MWh
Company Registered Address
Inkerman House
St Johns Road, Meadowfield
Durham
DH7 8XL
United Kingdom Date CFD Register Entry was Last Updated 01/11/2018 Allocation round Allocation Round 1
Unique Identifier AAA-BAN-192 Technology type Onshore Wind CFD Unit with Combined Heat and Power ("CHP") (yes/no) No Dual Scheme Plant
No
Capacity of Whole Station (applicable to Biomass conversions or dual schemes only)
0.00MW
Initial Installed Capacity Estimate for CFD Unit 60.00MW
Target Commissioning Date 31/03/2019 Target Commissioning Window Start Date 01/09/2018 Generator’s Expected Start Date 02/01/2019
Any Reduction to the Capacity of a CFD Unit 9.00MW
Company Registration No 7376956 Unique Geographical Coordinates N: 55.529, -3.798; E: 55.507, -3.779; S: 55.487, -3.796; W: 55.497, -3.828 CFD Agreement Type (Bespoke, Investment, Generic, Private Network, Phased (Single Metering) or Phased (Apportioned) Generic
Version Name and Number of Standard Terms Version: 1, 29 August 2014 Reference Number for Modification Agreement N/A
LCCC's Reasons for Accepting an Application to Modify the Standard Terms N/A Type of Connection (Partial, Direct or Islanded) Direct Transmission or Distribution connection Transmission