Relevant Dates
Date CFD Register Entry was Last Updated
Target Commissioning Date
Target Commissioning Window Start Date
Start Date
Strike price
Initial Strike Price
82.50£/MWh
Change to Strike Price (where applicable)
12.66£/MWh
Current strike price
95.16£/MWh
Project Information
Allocation round
Allocation Round 1
Technology type
Onshore Wind
CFD Unit with Combined Heat and Power ("CHP") (yes/no)
No
Dual Scheme Plant
No
Initial Installed Capacity Estimate for CFD Unit
39.10MW
Unique Geographical Coordinates
N: 57.400, -3.895; E: 57.386, -3.884; S: 57.383, -3.893; W: 57.392, -3.916
CFD Agreement Type (Bespoke, Investment, Generic, Private Network, Phased (Single Metering) or Phased (Apportioned)
Generic
Version Name and Number of Standard Terms
Version 1, 29 August 2014
Type of Connection (Partial, Direct or Islanded)
Direct
Transmission or Distribution connection
Distribution
"Licence Exempt Embedded" or "Licence Connected" (applies to distribution connected only)
Licence Exempt Embedded