Rebellion

Rebellion Biomass LLP

    Relevant Dates

    Date CFD Register Entry was Last Updated
    Target Commissioning Date
    Target Commissioning Window Start Date
    Generator’s Expected Start Date

    Strike price

    Initial Strike Price
    74.75£/MWh
    Change to Strike Price (where applicable)
    9.33£/MWh
    Current strike price
    84.08£/MWh

    Project Information

    Allocation round
    Allocation Round 2
    Technology type
    Dedicated Biomass with CHP
    CFD Unit with Combined Heat and Power ("CHP") (yes/no)
    Yes
    Dual Scheme Plant
    No
    Initial Installed Capacity Estimate for CFD Unit
    0.64MW
    Unique Geographical Coordinates
    N: 52.428, -1.661 E: 52.428, -1.660, S: 52.427, -1.661, W: 52.427, -1.664
    CFD Agreement Type (Bespoke, Investment, Generic, Private Network, Phased (Single Metering) or Phased (Apportioned)
    Private Network
    Version Name and Number of Standard Terms
    Version 2, March 2017
    Reference Number for Modification Agreement
    N/A
    Type of Connection (Partial, Direct or Islanded)
    Islanded
    Transmission or Distribution connection
    Distribution
    "Licence Exempt Embedded" or "Licence Connected" (applies to distribution connected only)
    Licence Exempt Embedded