Seagreen Phase 2

Seagreen Wind Energy Limited

    Relevant Dates

    Date CFD Register Entry was Last Updated
    Target Commissioning Date
    Target Commissioning Window Start Date
    Generator’s Expected Start Date

    Strike price

    Initial Strike Price
    41.61£/MWh

    Project Information

    Allocation round
    Allocation Round 3
    Technology type
    Offshore Wind
    CFD Unit with Combined Heat and Power ("CHP") (yes/no)
    No
    Dual Scheme Plant
    No
    Initial Installed Capacity Estimate for CFD Unit
    158.00MW
    Unique Geographical Coordinates
    N: 56.677, -1.603; E: 56.592, -1.528; S: 56.583, -1.708; W: 56.601, -1.765
    CFD Agreement Type (Bespoke, Investment, Generic, Private Network, Phased (Single Metering) or Phased (Apportioned)
    Phased (Single Metering)
    Version Name and Number of Standard Terms
    Version 3, 1 May 2019
    Reference Number for Modification Agreement
    N/A
    Type of Connection (Partial, Direct or Islanded)
    Direct
    Transmission or Distribution connection
    Transmission
    Single Metering or Apportioned Metering (applies to phased offshore wind only)
    Metered
    Offshore Leasing Round 2 or 3/Scottish Territorial Waters (applies to Offshore Wind only)
    Scottish Territorial Waters