Small Heath Bio Power Limited

Small Heath Bio Power Limited

    Relevant Dates

    Date CFD Register Entry was Last Updated
    Target Commissioning Date
    Target Commissioning Window Start Date
    Generator’s Expected Start Date

    Strike price

    Initial Strike Price
    41.61£/MWh

    Project Information

    Allocation round
    Allocation Round 3
    Technology type
    Advanced Conversion Technology
    CFD Unit with Combined Heat and Power ("CHP") (yes/no)
    No
    Dual Scheme Plant
    No
    Initial Installed Capacity Estimate for CFD Unit
    6.10MW
    Unique Geographical Coordinates
    N: 52.461, -1.842; E: 52.461, -1.840; S: 52.459, -1.842; W: 52.460, -1.842
    CFD Agreement Type (Bespoke, Investment, Generic, Private Network, Phased (Single Metering) or Phased (Apportioned)
    Private Network
    Version Name and Number of Standard Terms
    Version 3, 1 May 2019
    Reference Number for Modification Agreement
    N/A
    Type of Connection (Partial, Direct or Islanded)
    Islanded
    Transmission or Distribution connection
    Distribution