Sneddon Law Community Wind Farm

Sneddon Law Community Wind Company Limited

Relevant Dates

Date CFD Register Entry was Last Updated
Target Commissioning Date
Target Commissioning Window Start Date

Strike price

Initial Strike Price
79.99£/MWh
Change to Strike Price (where applicable)
11.60£/MWh
Current strike price
91.59£/MWh

Project Information

Allocation round
Allocation Round 1
Technology type
Onshore Wind
CFD Unit with Combined Heat and Power ("CHP") (yes/no)
No
Dual Scheme Plant
No
Initial Installed Capacity Estimate for CFD Unit
37.50MW
Any Reduction to the Capacity of a CFD Unit
7.50MW
Unique Geographical Coordinates
N: 55.665, -4.330; E: 55.665, -4.330; S: 55.645, -4.351; W: 55.651, -4.351
CFD Agreement Type (Bespoke, Investment, Generic, Private Network, Phased (Single Metering) or Phased (Apportioned)
Generic
Version Name and Number of Standard Terms
Version 1, 29 August 2014
Reference Number for Modification Agreement
N/A
Type of Connection (Partial, Direct or Islanded)
Direct
Transmission or Distribution connection
Distribution
"Licence Exempt Embedded" or "Licence Connected" (applies to distribution connected only)
Licence Exempt Embedded
General comments
LCCC is reviewing the CFD key dates in light of the project's revised construction schedule, currently being updated by the generator. The updated Generator's Expected Start Date will be published when available.