Relevant Dates
Date CFD Register Entry was Last Updated
Target Commissioning Date
Target Commissioning Window Start Date
Generator’s Expected Start Date
Strike price
Initial Strike Price
39.65£/MWh
Change to Strike Price (where applicable)
6.18£/MWh
Current strike price
45.83£/MWh
Project Information
Allocation round
Allocation Round 3
Technology type
Offshore Wind
CFD Unit with Combined Heat and Power ("CHP") (yes/no)
No
Dual Scheme Plant
No
Initial Installed Capacity Estimate for CFD Unit
364.00MW
Unique Geographical Coordinates
N: 55.080, 2.070; E: 54.901, 2.384; S: 54.839, 2.263; W: 55.011, 1.955
CFD Agreement Type (Bespoke, Investment, Generic, Private Network, Phased (Single Metering) or Phased (Apportioned)
Phased (Apportioned)
Version Name and Number of Standard Terms
Version 3, 1 May 2019
Reference Number for Modification Agreement
N/A
Type of Connection (Partial, Direct or Islanded)
Direct
Transmission or Distribution connection
Transmission
Single Metering or Apportioned Metering (applies to phased offshore wind only)
Apportioned
Offshore Leasing Round 2 or 3/Scottish Territorial Waters (applies to Offshore Wind only)
Round 3
General comments
Following the conclusion of the Judicial Review that was impacting all AR3 contracts, this contract was afforded a 6 month extension to the CFD milestones of Milestone Delivery Date, end of Target Commissioning Window and Longstop Date.