The "Initial Conditions Precedent (ICP) Guidance" Version 4.0 provides instructions for Generators on fulfilling ICPs under the CfD scheme, with updates for the sixth allocation round.
Key Points
- ICP Documentation Requirements: Generators must provide a legal opinion, detailed KYC information, and comprehensive facility descriptions .
- Process and Timeline: ICPs must be satisfied within 20 Business Days of the CfD Agreement Date, with submissions via LCCC's web-based application .
- Digital Submission: All required documents must be submitted through the Zero web-based application to ensure efficient processing and compliance tracking .
Updates from Previous Version
- Alignment with AR6: The guidance has been updated to reflect the terms and conditions specific to the sixth allocation round of the CfD .
- Hydrogen Production Facilities: New sections advise the inclusion of hydrogen production facility descriptions, indicating an expansion of the scope to cover emerging technologies in the energy sector .
- Digital Submission Process: Emphasis on the use of the Zero web-based application for submitting ICP documents, enhancing the efficiency and accuracy of compliance submissions