LCHA Milestone Requirement Guidance
Posted 21.02.2025
The "Milestone Requirement Guidance" provides instructions for Producers on fulfilling the Milestone Requirement under the LCHA via either the “10% spend” route or “Project Commitments” route.
Key Points
- Requirements: Producers must provide evidence that they have either spent at least 10% of the Total Project Pre-Commissioning Costs, or that they have fulfilled the Project Commitments set out in the LCHA. Producers may also have additional project-specific requirements as outlined in Annex 3 of the LCHA Front-End Agreement.
- Timeline: The Milestone Requirement must be satisfied by the Milestone Delivery Date: 12 months (for Electrolytic Facilities) or 18 months (for CCUS-Enabled Facilities) after the LCHA Agreement Date.
- Submission: All required documents must be submitted via LCCC's web-based application, Zero.
LCHA Milestone Requirement Guidance
Quick Links
Contact Us
For enquiries or to speak to a member of the team, please fill in the contact form and we'll get back to you as soon as possible.
FAQs
View all frequently asked questions and our responses for our schemes and other resources.